SEC logo
News

Giant transformers to connect SEC’s big battery to the grid

19 January 2025

Two giant transformers have arrived in Victoria and will be used to connect the SEC’s first project – one of the world’s biggest batteries – to the grid.

Weighing a massive 335 tonnes each, the transformers travelled from the Port of Melbourne to the Melbourne Renewable Energy Hub in Plumpton with an oversized load escort in the early hours of the morning to avoid traffic disruption.

A specialised crew worked over three days to complete a precise ‘jack and skate’ process, lifting the transformers and gliding them on to their foundations. A third transformer arrives soon and will undergo the same process, while work continues to connect the first two transformers.

“We’re excited to see the SEC’s first project take shape and continue to achieve construction milestones,” the SEC General Manager Asset Delivery, David Moo, said.

“The transformers being installed will enable the Melbourne Renewable Energy Hub to deliver up to 1.6 gigawatt hours of energy storage onto the grid - enough to power 200,000 homes during peak periods.”

A transformer is an essential piece of equipment for any renewable energy generation or storage project, allowing energy to be sent to the transmission network at a higher voltage, maximising grid performance and reducing transmission losses over long distances. In the case of the Hub, this will enable reliable transmission of energy to Victorian households.

In an Australian-first for a battery energy storage connection, a 1.75 kilometre underground 500 kilovolt cable will be used to connect the project to the grid via the Sydenham Terminal Station.

On track to be operational later this year, the Hub is co-owned with renewable energy investor Equis Australia.

The project recently reached a significant construction milestone with all the site’s 444 battery units now in place. The units form three giant battery components that will ultimately strengthen Victoria’s electricity network.

Since construction began in late 2023, more than 790 people have worked across all aspects of the project, including 30 apprentices, trainees and cadets.

Latest news:

SEC Delburn Wind Farm

Gippsland locals powering ahead with construction of SEC Delburn Wind Farm

24 August 2026

It’s been more than six months since the first sod was turned at the SEC Delburn Wind Farm and the project is not only rapidly taking shape but also providing significant benefits for local businesses and workers.

SEC: delivering for the Latrobe Valley and beyond

20 August 2026

For over a century the Latrobe Valley has been at the heart of Victoria’s power generation With its highly skilled energy workforce and unparalleled access to Victoria’s transmission network, the region will continue to play a critical role as the state advances a once-in-a-century energy transition.

Jack at SEC Delburn Wind Farm

Jack’s journey helping build Latrobe Valley’s energy future

17 August 2026

Mirboo North local Jack Burgess-Pincini is playing a hands-on role bringing one of the Latrobe Valley’s most significant renewable energy projects, the SEC Delburn Wind Farm, from concept to reality.

GNEC

Joining the conversation on Gippsland’s energy future

12 August 2026

SEC will be at the Gippsland New Energy Conference (GNEC) in Traralgon on 18 and 19 August, joining industry, government and community leaders to explore the opportunities emerging from Victoria’s energy transition.